With most Hospitals, disruption is at the forefront of operations. We were appointed to remove and replace all hot and cold water services to several wards for a period of the year.

This included DDA Showers, Staff Rest area, Clinical washing facilities, Clean & Dirty Utility areas.

New pipework runs were installed from the hospitals central services and fed to these areas on each ward. Extra care had to be taken on pipework routes and we had to include a new Hot Water return system to ensure hot water was available quickly at each outlet.

On each of the 4 wards, we only had 3 months for the entire refit and had to work around other trades during those times. Our work was delivered on time and in budget,