Projects

Redriff primary school (5).jpg

Redriff Primary School

The school has two plantrooms North and South, the North plantroom boilers with their associated flues had to be swapped out for four new 100kw Hamworthy Purewell Variheat condensing boilers during the summer break, we had two weeks to complete the project which was carried out seamlessly.

Then came the South plantroom and two further boiler swaps in which we only had 9 days to complete during the October half-term break. This project was successfully delivered on time and in budget.